| 1 | <?xml version="1.0"?> |
|---|
| 2 | <project name="" company="" manager="" phase="" project-start="20051205T000000Z" mrproject-version="2" calendar="1"> |
|---|
| 3 | <properties/> |
|---|
| 4 | <phases/> |
|---|
| 5 | <calendars> |
|---|
| 6 | <day-types> |
|---|
| 7 | <day-type id="0" name="Working" description="A default working day"/> |
|---|
| 8 | <day-type id="1" name="Nonworking" description="A default non working day"/> |
|---|
| 9 | <day-type id="2" name="Use base" description="Use day from base calendar"/> |
|---|
| 10 | </day-types> |
|---|
| 11 | <calendar id="1" name="Default"> |
|---|
| 12 | <default-week mon="0" tue="0" wed="0" thu="0" fri="0" sat="1" sun="1"/> |
|---|
| 13 | <overridden-day-types> |
|---|
| 14 | <overridden-day-type id="0"> |
|---|
| 15 | <interval start="0800" end="1200"/> |
|---|
| 16 | <interval start="1300" end="1700"/> |
|---|
| 17 | </overridden-day-type> |
|---|
| 18 | </overridden-day-types> |
|---|
| 19 | <days/> |
|---|
| 20 | </calendar> |
|---|
| 21 | </calendars> |
|---|
| 22 | <tasks> |
|---|
| 23 | <task id="1" name="Campaign Wizard" note="" work="115200" start="20051207T170000Z" end="20051213T170000Z" work-start="20051208T080000Z" percent-complete="100" priority="3" type="normal" scheduling="fixed-work"> |
|---|
| 24 | <predecessors> |
|---|
| 25 | <predecessor id="1" predecessor-id="3" type="FS"/> |
|---|
| 26 | </predecessors> |
|---|
| 27 | </task> |
|---|
| 28 | <task id="2" name="Upload Manager" note="" work="43200" start="20051205T000000Z" end="20051206T120000Z" work-start="20051205T080000Z" percent-complete="100" priority="0" type="normal" scheduling="fixed-work"/> |
|---|
| 29 | <task id="3" name="Refactor List Management" note="" work="43200" start="20051206T120000Z" end="20051207T170000Z" work-start="20051206T130000Z" percent-complete="100" priority="0" type="normal" scheduling="fixed-work"> |
|---|
| 30 | <predecessors> |
|---|
| 31 | <predecessor id="1" predecessor-id="2" type="FS"/> |
|---|
| 32 | </predecessors> |
|---|
| 33 | </task> |
|---|
| 34 | <task id="4" name="Resource Profiles" note="" work="28800" start="20051216T170000Z" end="20051219T170000Z" work-start="20051219T080000Z" percent-complete="100" priority="0" type="normal" scheduling="fixed-work"> |
|---|
| 35 | <predecessors> |
|---|
| 36 | <predecessor id="1" predecessor-id="8" type="FS"/> |
|---|
| 37 | </predecessors> |
|---|
| 38 | </task> |
|---|
| 39 | <task id="5" name="Resource Profile Wizard" note="" work="25200" start="20051219T170000Z" end="20051220T160000Z" work-start="20051220T080000Z" percent-complete="0" priority="0" type="normal" scheduling="fixed-work"> |
|---|
| 40 | <predecessors> |
|---|
| 41 | <predecessor id="1" predecessor-id="4" type="FS"/> |
|---|
| 42 | </predecessors> |
|---|
| 43 | </task> |
|---|
| 44 | <task id="6" name="Redirection Manager" note="" work="14400" start="20051220T160000Z" end="20051221T110000Z" work-start="20051220T160000Z" percent-complete="50" priority="0" type="normal" scheduling="fixed-work"> |
|---|
| 45 | <predecessors> |
|---|
| 46 | <predecessor id="1" predecessor-id="5" type="FS"/> |
|---|
| 47 | </predecessors> |
|---|
| 48 | </task> |
|---|
| 49 | <task id="7" name="List Filtering for Campaigns" note="" work="30600" start="20051213T170000Z" end="20051215T083000Z" work-start="20051214T080000Z" percent-complete="100" priority="2" type="normal" scheduling="fixed-work"> |
|---|
| 50 | <predecessors> |
|---|
| 51 | <predecessor id="1" predecessor-id="1" type="FS"/> |
|---|
| 52 | </predecessors> |
|---|
| 53 | </task> |
|---|
| 54 | <task id="8" name="Creative Import" note="" work="27000" start="20051216T083000Z" end="20051216T170000Z" work-start="20051216T083000Z" percent-complete="100" priority="0" type="normal" scheduling="fixed-work"> |
|---|
| 55 | <predecessors> |
|---|
| 56 | <predecessor id="1" predecessor-id="9" type="FS"/> |
|---|
| 57 | </predecessors> |
|---|
| 58 | </task> |
|---|
| 59 | <task id="9" name="Refactor List Import" note="" work="28800" start="20051215T083000Z" end="20051216T083000Z" work-start="20051215T083000Z" percent-complete="100" priority="0" type="normal" scheduling="fixed-work"> |
|---|
| 60 | <predecessors> |
|---|
| 61 | <predecessor id="1" predecessor-id="7" type="FS"/> |
|---|
| 62 | </predecessors> |
|---|
| 63 | </task> |
|---|
| 64 | </tasks> |
|---|
| 65 | <resource-groups/> |
|---|
| 66 | <resources> |
|---|
| 67 | <resource id="1" name="Scott S. McCoy" short-name="Scott" type="1" units="0" email="scott@mushoo.com" note="" std-rate="0"/> |
|---|
| 68 | </resources> |
|---|
| 69 | <allocations> |
|---|
| 70 | <allocation task-id="9" resource-id="1" units="100"/> |
|---|
| 71 | <allocation task-id="8" resource-id="1" units="100"/> |
|---|
| 72 | <allocation task-id="7" resource-id="1" units="100"/> |
|---|
| 73 | <allocation task-id="6" resource-id="1" units="100"/> |
|---|
| 74 | <allocation task-id="5" resource-id="1" units="100"/> |
|---|
| 75 | <allocation task-id="4" resource-id="1" units="100"/> |
|---|
| 76 | <allocation task-id="1" resource-id="1" units="100"/> |
|---|
| 77 | </allocations> |
|---|
| 78 | </project> |
|---|